The following is a brief description of the work phases completed and in progress at the mill.
1. (Completed)
|
a. Building Foundation Stabilization.
b. Perimeter Foundation and RWC - East and South Elevations of Existing Mill.
c. Site Utility Excavation & Installation - Sanitary, Water, Electric, Telephone, and Fire protection.
d. Exterior Demolition - East and South Elevations of existing Mill.
e. Construct Stair B and Stair C South Elevations of Existing Mill.
f. Construct Elevator Pit.
g. Construct Interior Partition Walls - 1st, 2nd & Mezzanine Level of Existing Mill.
h. Construct Stair D West Elevation of Existing Mill.
|
)
|
2. (Completed)
|
a. Exterior Demolition - West Elevations of Existing Mill.
b. Perimeter Foundation and RWC - West Elevations of Existing Mill.
c. Interior Demolition- 1st, 2nd & Mezzanine Level of Existing Mill
d. Install Warmboard and Radiant Tubing- 1st and 2nd Floor.
e. Interior Demolition & Excavation - Grade Level & Stair Tower A of Existing Mill.
f. Construct Elevated Slab Heated Tubing - Grade Level of Existing Mill.
g. Install Radiant Slab Heating Tubing - Grade Level of Existing Mill.
h. Underslab Mechanical Rough-in - Grade Level of Existing Mill.
i. Install Concrete Floor Slabs - Grade Level of Existing Mill.
j. Construct Stair A and Railing System 1.
k. Construct Interior Partition Walls - Grade Level.
l. Mechanical Rough-in - All Levels of Existing Mill.
m. Construct Stair Tower E.
n. Install Boiler & Recovery Ventilation System #1 - All Levels of Existing Mill.
o.Install Elevator and Elevator Tower.
p. Re-point and repair Masonry Exterior East and South Elevations of Existing Mill.
q. Install insulation - All Levels of Existing Mill.
r. Construct Stair Tower E Railing System.
s. Install Interior Sprinkler System - All Levels of Existing Mill.
|

|
3. (In Progress)
|
a. Exterior Demolition (Completed) - North Elevations of Existing Mill.
b. Re-point and Repair Masonry Exterior North Elevations of Existing Mill.
c. Re-point and repair Masonry Exterior - West Elevations of Existing Mill.
d. Installed fire escape (Completed) - West Elevation of Existing Mill
e. Interior Masonry Restorations (In Progress) - grade 1st, 2nd, & Mezzanine Level of Existing Mill.
f. Install sound attenuation and drywall (In Progress) - All Levels of Existing Mill.
g. Install Doors, Windows and Hardware (In Progress) - All Levels of Existing Mill.
h. Mill Install Finishes (In Progress) - All Levels of Existing Mill.
i. Install Cabinetry - All Levels of Existing Mill.
j. Exterior Wood Patching and Painting (In Progress) - All Levels of Existing Mill.
k. Re-grading, Landscaping, and Paving. (In Progress)
l. Complete Electrical Wiring and Finishes. (In Progress)
|

|
|
|
|